Our customer has invested three years to develop the system. But the system has been developed in an unstructured way, without Version control, without SDD and without Bug Reports.
The current system has more than 60 bugs, identified by AMM. Some of these bugs impacted the heating cycle and thereby the composite curing process that led to rejection of specimen.
AMM implemented GIT for Version control.
The first plant has been delivered to a Tier-1 supplier of Airbus, 4 weeks after the project started.